MVE in the Jesenice water

Performing technical supervision of the builder and ensuring the activities of the OSH coordinator in the implementation of a small hydroelectric power plant.

Klient

Water treatment plant Želivka a.s. (Voda Želivka, a.s.)

Datum realizace

2020 - 2022

Investiční náklady

117 miles. CZK excl. VAT

The object of construction was the installation of four sets of a small hydroelectric power plant. In each of the water reservoirs Jesenice 1 and Jesenice 2, 2 sets with a Francis turbine were installed in the existing inflow armature chambers to drive the generator for power generation. The total power of the MVE was 1 MW.

Within the scope of this contract, the technical supervision of the builder and the activities of the OSH coordinator in the implementation of a small hydroelectric power plant were ensured.

‍

Realize your project with experts

Our experience and many years of practice in the field guarantee that your project will be implemented with maximum precision and consideration for sustainability.